Skip to main content
Knowledge Profile
ReportedPublished

Expected combined investment of over $200 million across DC BLOX SC footprint.

Knowledge
37/100
Evidence
0/100
Freshness
100/100
Relationships
45/100
Completeness
30/100
Transparency
10/100
Evidence
0
Timeline
0
Relationships
3
Last Reviewed
Jul 22, 2026

DC BLOX Greenville County Data Center

Operating◆ confirmedData Center
Greenville, Greenville County Last Updated: Jun 15, 2026 0 Public Sources
Brief

Executive Summary

Expected combined investment of over $200 million across DC BLOX SC footprint.
Metrics

Project Snapshot

Key project metrics at a glance.

Estimated Investment
$200M+
Estimated Jobs
Power Demand
Water Demand
Site Acreage
Project Status
operating
Utilities

Cooling, Water & Electricity

Power, cooling, water, and wastewater for this project.

Utilities

Cooling, Water & Electricity

How this project is powered, cooled, and connected to local water and wastewater systems. Figures are drawn from public records and developer disclosures.

IT Cooling & Heat Rejection

Data centers remove heat in two stages: first from the servers (IT cooling), then from the building to the outdoors (heat rejection). The methods chosen drive water use, energy overhead, and neighborhood noise.

IT equipment
Direct Expansion (DX)
Heat rejection
Unknown
Atmosphere
IT cooling method
Direct Expansion (DX)
Heat-rejection method
Unknown
Cooling tower present
False
Closed-loop claimed
True
Economizer (free cooling)
Unknown
Hybrid capability
No

Water Source & Demand

Data centers use water mainly for evaporative cooling and humidification. The source, quality, and use of reclaimed water determine the impact on local supply and aquatic systems.

Source: Surface Water
Unknown
Facility
Discharge
Water provider
Greenville Water
Provider type
Unknown
Primary source
Surface Water
Cooling-water quality
Unknown
Average daily demand
2,740 gal/day
Annual demand
1,000,000 gal/year
Provider upgrade required
Unknown

Wastewater Discharge

Water leaving the site is treated on-site, sent to a municipal plant, discharged directly, or evaporated. Zero-liquid-discharge (ZLD) systems eliminate liquid discharge entirely.

Facility
Sewer
Environment
Wastewater provider
Renewable Water Resources (ReWa)
Discharge method
Sewer
Upgrade required
Unknown

Electric Provider & Interconnection

A data center is among the largest electric loads a utility can serve. Demand is measured in megawatts; PUE relates total facility power to IT power (1.0 means all power reaches the IT equipment).

Grid
Substation
Facility
IT load 1 MW
Retail provider
Duke Energy Carolinas
Provider type
Unknown
Initial demand
3 MW
Full-buildout demand
18 MW
IT load
1 MW
Interconnection status
Unknown
Substation upgrade required
Unknown
Transmission upgrade required
Unknown
Backup fuel
Diesel
Battery storage
1.45 MWh
Demand-response participation
Unknown

Renewable Energy Claims

Renewable claims describe how a facility matches its consumption with clean generation. The geography and matching method determine whether the claim reflects new, local clean energy or paper certificates.

Unknown
Matching
Facility
Renewable claim
False
Claim type
Unknown
Claim geography
Unknown
Officially AnnouncedConfidence: MediumVerified: Jul 27, 2026
Chronology

Project Timeline

Chronological history of project milestones and public activity.

This activity timeline is currently being expanded as additional public information becomes available.

Geography

Project Location

Geographic location and transportation context.

Geographic Location

Exact project boundary not yet verified.

Greenville, Greenville County
Google Maps
Municipality
Greenville
Nearby Transportation
Being verified
Sources

Research Library

Public sources and research articles associated with this project.

https://www.dcblox.com

Other
Open
Press

News & Public Information

Chronological list of public news articles.

Research for this project is currently being expanded.

Records

Public Documents

Downloadable public resources and official records.

Planning Documents

Not yet available

Rezoning Documents

Not yet available

Meeting Minutes

Not yet available

Utility Filings

Not yet available

Environmental Reports

Not yet available

Developer Presentations

Not yet available

Community

Questions Communities Often Ask

Common questions about digital infrastructure projects.

Knowledge Graph

Related Resources

Discover connected organizations, projects, research, and policy across the platform.

Community

Help Improve This Resource

The Alliance continuously improves project information through public records and community contributions.

If you know of additional public information or believe this page can be improved, we encourage your participation.

Relationship Graph4 connections
Counties (1)
Greenville
LOCATED_IN · outgoing · high
Organizations (3)
Duke Energy
SERVES · incoming · high
Duke Energy
SERVES · incoming · high
DC BLOX